Background
NorthGrid Energy distributes electricity to over 740,000 residential and commercial customers across Ontario and Manitoba, operating a field workforce of 620 technicians responsible for maintenance, outage response, meter installation, and safety inspections across a combined service territory of 180,000 square kilometres. At those distances and in those winters, operational efficiency isn't just a business metric — it's a safety imperative.
Yet NorthGrid's field operations were almost entirely paper-driven. Work orders were printed and handed to technicians at depot, job updates were radioed back to dispatch, and post-job documentation was completed manually and physically returned for data entry. Emergency fault calls averaged 4 hours from report to technician on-site — a figure that had attracted regulatory scrutiny from the Ontario Energy Board. NorthGrid engaged Gagstek to implement Salesforce Field Service Lightning and modernise every layer of their field operations, from intelligent scheduling through to mobile-first job completion and real-time GIS asset integration.
Operational Scale
Key Business Challenges
NorthGrid's operational fragmentation had compounded over decades of legacy systems and organic growth. By the time Gagstek's discovery team arrived, the business was running on six separate tools with no shared data layer.
Gagstek's Solution
Gagstek structured the implementation in four phases over 18 weeks, prioritising emergency dispatch capability in Phase 1 given its regulatory urgency, then progressively rolling out mobile, GIS integration, and predictive maintenance across the subsequent phases.
Delivery Approach
With 620 technicians and 28 depot locations across two provinces, a big-bang go-live was never an option. Gagstek designed a phased rollout that delivered regulatory-critical capability first, then systematically expanded across the workforce and territory.
Business Impact
Client Testimonial
"We were under real pressure from the OEB on response times, and we knew our paper-based processes were the root cause — but the scale of the challenge felt enormous. 620 technicians, 28 depots, two provinces. Gagstek didn't flinch. They phased the rollout intelligently, got our emergency response metric into compliance within the first month, and had every technician on mobile within 14 weeks. The GIS integration was the piece that surprised our field teams most — they couldn't believe they could pull up full asset history and network schematics from their phone on a pole in Northern Manitoba. That capability alone changed how our people work."